The framing is 90% done and this week we started the HVAC, Electrical and rough-in plumbing. Lots of work. Windows are schedule to arrive on Monday and Lindsay and I are really excited for that!

This is a shot that Kaya sent us. I think the house will be "wrapped" next week, so this may be your last shot of the plywood exterior.

The plumber roughed in the sinks and shower in the master bathroom, and the electrician ran wiring for the new lights. The guys are standing in the bathroom, the picture was taken from the master bedroom.

Here is a shot of the ceiling of the master bedroom. They ran the HVAC tubing through the joists due to the fact that we didn't want anything blocking the windows. The HVAC guy said he'd never cut so many holes in the joists before (Lindsay and I laughed nervously). They also put up the roof venting, which looks like its made of egg crate material. The underside will be insulated and then drywalled, but the venting creates a small channel that will allow air to pass between the insulation and the roof.